Project Scope
===========
Total road length planned covers over 104KM. To be completed in three phases:
1. Phase 1:
Maychekemte (15 km) and May Abeba to Hibret (25 km).
2. Phase 2:
Adishmbello to Seria (11.5 km).
3. Phase 3:
Tsaee and Hagereselam (45 km & 11 km). Cost:
=====
The total budget for the 1st and 2nd phases is 50 million birr . Construction Machinery
=================
All if not most machinery required are available for free(Thanks to Hayli Tigray) More…
======
There will be about 19 fords to be built need if the road is to withstand erosion effects!
Thank you. (Source From Edaga Arbi Officials via Solomon)